Cooling Plant Replacement Options Study

12,000 m2 office building: which system should we install?

Client
Example Contractors Ltd (fictional mid-size MEP contractor)
Prepared by
Pro Solutors
Reference
PS-SAMPLE-001
Edition
Sample, October 2026
Two engineers with a tablet reviewing plant equipment and process pipework on site
Sample - Fictional company

This is an illustrative sample. The company, project and all figures are fictional and are not real client data or real client results. It shows the structure and standard of our reports.

01

The result at a glance

900 kW
design cooling load after load review
1,980k
10-year cost of the recommended option (USD)
77 / 100
weighted score of the recommended option
7 to 8 yrs
payback of the extra upfront cost
Result at a glance
ItemDetail
ClientExample Contractors Ltd (fictional mid-size MEP contractor)
Our solutionSolve and Prove
DurationOptions study with a 5-week decision window
OutcomeOption C (water-cooled chillers with cooling towers) has the lowest 10-year cost and the highest score, subject to a roof check and a secure water supply.

All results are fictional and illustrative.

02

The challenge

The building is a six-storey office of about 12,000 m2, occupied throughout the year. Cooling comes from two air-cooled chillers installed more than 25 years ago, serving a chilled-water loop to fan-coil and air-handling units. The building stays occupied, shutdowns are only possible at weekends, the upfront budget cap is about 800k and new plant must run before next summer, about 9 months away.

  • Reliability

    11 breakdown call-outs in the last 24 months; two days of reduced cooling in the hottest weeks.

  • Refrigerant

    The units use an older refrigerant that is being phased out, so repairs and recharging are becoming harder and more costly.

  • Running cost

    Energy use per m2 is well above comparable buildings, and efficiency is falling each year.

  • Sizing

    Original design assumed 1,000 kW. A load review gives a peak of 900 kW, so a like-for-like replacement would be oversized.

03

Our approach

  1. Check the load

    Confirm the 900 kW peak before sizing anything.

  2. Shortlist

    Three options that fit the site and budget cap: air-cooled chillers, a VRF system, and water-cooled chillers with towers.

  3. Cost model

    Capital, energy and maintenance over 10 years.

  4. Stress test

    Repeat the model with energy prices rising 3% and 6% a year.

  5. Score

    Rate each option 1 to 5 on six weighted criteria agreed before any prices were seen.

  6. Risk review

    List what could go wrong with the leading option and how to control it.

04

The roadmap

  1. Step 1 · Weeks 1 to 2

    Verify

    Roof structure, water supply, plant room access

    Goal: Confirm Option C is possible

  2. Step 2 · Weeks 3 to 4

    Price

    Fixed-price quotes from three suppliers

    Goal: Update the cost model

  3. Step 3 · Week 5

    Decide

    Final decision

    Goal: Option C, or Option A if a condition failed

  4. Step 4 · Months 2 to 3

    Procure

    Tender, long-lead order, shutdown windows

    Goal: Secure equipment and dates

  5. Step 5 · Months 4 to 8

    Install

    Two weekend phases, commissioning

    Goal: Hand over with a maintenance plan

05

The evidence and results

Results
OptionCapital (USD k)10-year total (USD k)Weighted score
A. Air-cooled chillers6202,02072 / 100
B. VRF system5402,19062 / 100
C. Water-cooled + towers7801,98077 / 100

Recommendation: Option C, water-cooled chillers with cooling towers

It has the lowest 10-year cost (1,980k against 2,020k for Option A and 2,190k for Option B at today's energy prices) and the highest score. The advantage grows to 141k over Option A if energy prices rise 6% a year. It is recommended only if the roof passes a structural check and a secure water supply is confirmed. If either fails, choose Option A. Do not choose Option B.
10-year cost at flat energy prices (USD thousands)

The gap between Option C and Option A is 40k at flat prices, 87k at +3% a year and 141k at +6% a year. Higher energy prices only strengthen the recommendation.

10-year cost at flat energy prices (USD thousands)
PeriodValue
A. Air-cooled2,020k
B. VRF2,190k
C. Water-cooled1,980k

06

Main risks and how to control them

  • Cost overrun on a 1,980k option (medium)

    Get fixed-price supplier quotes before tender; hold a 5% contingency.

  • Delay to long-lead chillers (high)

    Place the equipment order early; confirm delivery dates in writing.

  • Failure during weekend shutdown work (medium)

    Phase the work over two weekends; keep a temporary chiller on standby.

  • Higher maintenance with cooling towers (medium)

    Agree a service contract and water treatment plan at purchase.

07

Conditions to confirm first

  • Roof structure: a structural engineer confirms the roof can carry the cooling towers.
  • Water supply: a reliable supply and a water treatment plan are confirmed.
  • Plant room access: a route exists to remove the old chillers and bring in the new ones.

Assumptions and limits

  • All prices, energy figures and the building itself are fictional and for illustration only.
  • Costs are undiscounted and ignore inflation, except in the energy price tests shown.
  • This study compares options. It is not a detailed design or a construction price.
  • In a real project, every figure would come from the client data and supplier quotes.

This is an illustrative sample. The company, project and all figures are fictional and are not real client data or real client results. It shows the structure and standard of our reports.

Feasibility Proof Report

Tell us the decision you face. An engineer reads it and tells you clearly whether a feasibility proof report would help.

What happens after you submit

  1. Problem received

    You describe it through the form.

  2. Read by an engineer

    Every submission is read by an engineer.

  3. A clear yes or no, and a next step

    You hear back within 2 working days.